Flooring, Painting & Kitchen Cabinets: The Exact Renovation Order of Works 

Planning a home renovation involves more than choosing the right flooring, paint colours and kitchen cabinets. The order in which these jobs are completed can affect the final finish, installation quality, project costs and the amount of rework required. Installing flooring too early, painting before dusty work is finished or fitting cabinets without considering the floor type can lead to avoidable damage, delays and additional expenses.

In this guide, we'll explain the correct renovation order for flooring, painting and kitchen cabinets, including when each trade should begin and how different flooring materials affect the sequence. You'll also learn when to install cabinets before or after flooring, how to protect finished surfaces and which finishing tasks should come last.

What Is the Correct Order of Works for Flooring, Painting and Kitchen Cabinets?

The correct order for flooring, painting and kitchen cabinets depends on the flooring installation method, but most renovations should begin with planning, demolition and structural work before moving to surface preparation, painting, cabinetry and flooring. Completing dusty and disruptive tasks first helps protect new finishes, while coordinating cabinet and flooring installation prevents movement restrictions, height mismatches and unnecessary rework.

The following sequence provides a practical starting point for planning a kitchen or home renovation:

Stage

Work

Main purpose

1

Planning and measurements

Confirm floor type, cabinet dimensions, finished floor height and trade schedule

2

Demolition and removal

Remove old flooring, cabinets and finishes where required

3

Structural, plumbing and electrical work

Complete layout changes and service rough-ins

4

Wall and ceiling repairs

Plaster, patch, sand and prepare surfaces

5

Initial painting

Paint ceilings and walls before installing vulnerable finished floors

6

Kitchen cabinetry

Install fixed cabinets first when required by the flooring system

7

Flooring installation

Install flooring according to its fixing method and manufacturer instructions

8

Final finishing

Complete kickboards, skirting, paint touch-ups, trims and final fit-off

Important: This is a general planning sequence, not a fixed rule for every renovation. Floating floors usually need to move freely and should not be trapped beneath fixed kitchen cabinets or islands. In contrast, some glue-down flooring systems can be installed before cabinetry, allowing cabinets to sit on the finished floor. Always confirm the required sequence with the flooring manufacturer and installer before work begins.

Explore Our Hybrid Flooring

Why should renovation work follow a planned sequence?

Renovation work should follow a planned sequence because each trade can affect the surfaces and measurements needed by the next. Painting after major dusty work reduces the risk of dust settling on wet paint, while installing cabinets before a floating floor prevents the fixed units from restricting the floor's natural movement.

For example, cabinet installation can cause scratches, dents and impact damage if new flooring is already exposed. Painters may also need to touch up walls after cabinetry is fitted, particularly around cabinet edges, bulkheads and trim. If the finished floor height is not considered during cabinet planning, appliances, kickboards and benchtop clearances may not fit as intended.

A planned sequence also helps trades coordinate their measurements and installation dates. Cabinetmakers need accurate dimensions and service locations, while flooring installers need a clean, dry and level subfloor. Completing these preparations before installation reduces the likelihood of delays, additional labour and avoidable material damage.

Which renovation tasks should be completed before painting, cabinetry and flooring?

Complete demolition, structural changes, plumbing and electrical rough-ins, wall repairs and subfloor preparation before installing the final finishes. These tasks often create dust, debris or changes to the room's dimensions, so completing them early helps protect paint, cabinets and new flooring.

The main preparation tasks include:

  • Demolition and removal: Remove old cabinets, flooring, tiles, skirting and other finishes that need replacing. Clear construction waste and inspect the exposed surfaces before starting new work.

  • Structural changes: Complete wall removals, framing, doorway changes, bulkhead work and other building modifications. Any structural work should be completed before final measurements and finishes.

  • Plumbing and electrical rough-ins: Relocate or install water pipes, drainage, power points, lighting, switches and appliance connections. Licensed trades should complete regulated plumbing and electrical work before walls and floors are closed or finished.

  • Wall and ceiling preparation: Repair plasterboard, fill cracks, patch damaged areas and sand uneven surfaces. Remove sanding dust before applying primer and paint.

  • Subfloor inspection and preparation: Check the subfloor for moisture, uneven areas, cracks, contamination and structural problems. Complete any required levelling, repairs or moisture treatment before flooring installation.

  • Cabinet and appliance measurements: Confirm cabinet dimensions, benchtop height, appliance openings, plumbing locations and the planned finished floor height. These measurements help prevent clearance and fitting problems later.

Do not leave subfloor preparation until the flooring installer arrives. The flooring system needs a suitable base, and some repairs or levelling compounds require time to cure before installation. Once the preparation work is complete, the project can move into painting, cabinetry and flooring in the order suited to the selected materials.

Explore Our Timber Flooring

Should You Paint Before or After Installing Kitchen Cabinets and Flooring?

You should complete most wall and ceiling painting before installing new flooring to reduce the risk of paint splashes, sanding dust, scratches and damage to finished surfaces. Kitchen cabinet installation should be coordinated with the painting schedule so painters can reach accessible wall areas before the cabinets are fitted. Once the flooring and cabinetry are installed, complete any remaining cut-ins, skirting, trim work and paint touch-ups.

This approach separates the main painting work from the final finishing stage. It also helps prevent painters from working around newly installed floors and fitted cabinets unnecessarily.

Why should walls and ceilings be painted before new flooring?

Walls and ceilings should be painted before new flooring because painting involves activities that can damage or contaminate finished floor surfaces. Paint drips, sanding dust, ladders, paint trays, tools and repeated foot traffic can leave marks on carpet, timber, laminate, vinyl and hybrid flooring.

Even when installers cover the floor, protective sheets cannot eliminate every risk. Dust and paint can enter exposed edges or gaps, while moving ladders and equipment can scratch or dent some surfaces. Carpet is particularly difficult to clean if wet paint reaches its fibres.

Completing ceiling and wall preparation first also allows painters to sand, patch and apply paint without working around the newly installed floor. Once the main painting work is dry, the renovation can move to cabinetry and flooring installation according to the selected flooring system.

Before flooring installation, remove paint residue, construction dust and debris from the subfloor. The surface should be clean, dry and prepared to meet the flooring manufacturer's requirements.

Ready to Transform Your Home's Flooring?

Get expert guidance on carpets, hybrid, timber, vinyl & laminate flooring. Book a free in-home consultation with our specialists today!

Should you paint the walls before or after installing kitchen cabinets?

You should paint accessible wall areas before installing kitchen cabinets because empty walls are easier to prepare, prime and paint. Painters can cover larger surfaces without working around cabinet frames, benchtops, appliances and other fixed fittings.

Painting before cabinetry also reduces the need to reach narrow spaces behind cupboards or work around finished cabinet surfaces. This is particularly useful when installing full-height pantry units, overhead cabinets and cabinetry that extends close to walls or ceilings.

However, the initial paintwork may not complete every visible area. Cabinet installation can expose small gaps, edges or sections that need additional cutting-in and touch-ups. Painters may also need to repair minor marks caused by drilling, levelling and fixing the cabinets to the walls.

A practical approach is to:

  1. Complete wall repairs, sanding, priming and the main paint coats before cabinet installation.

  2. Allow the paint to dry according to the product instructions before other trades begin working against the walls.

  3. Install and level the kitchen cabinets, then complete benchtop and appliance fitting as scheduled.

  4. Return for final paint touch-ups around exposed edges, cabinet panels, bulkheads and other affected areas.

Protect finished cabinet doors, benchtops and surrounding surfaces during these final painting tasks.

When should you paint skirting boards, trims and cabinet kickboards?

Paint skirting boards and trims during the final finishing stage when their installation depends on the completed flooring. Cabinet kickboards are generally fitted or adjusted after flooring installation when the kitchen design requires them to meet the finished floor level.

Skirting boards cover the expansion gap between the wall and flooring in installations that require one. Their position and installation method depend on the floor type. Some skirting boards can be installed and painted before flooring, while others are fitted after the floor to achieve a neat finish. Any required expansion clearance must remain unobstructed.

Cabinet kickboards, also called plinths, cover the space beneath kitchen cabinets and create a finished appearance. Installers generally fit or adjust them after the flooring is complete so they align with the final floor height. The exact method depends on the cabinet design and flooring system.

The final finishing stage typically includes:

  • Skirting boards: Install or refit them at the appropriate stage, then fill, sand and touch up paint where needed.

  • Door frames and architraves: Complete any cuts, repairs or paint touch-ups required after flooring installation.

  • Cabinet kickboards: Fit or adjust them to suit the finished floor level and cabinet design.

  • Cabinet edges and wall junctions: Complete small paint corrections around exposed areas without marking finished surfaces.

Separating the main painting stage from final touch-ups helps achieve a cleaner finish while reducing the risk of damaging new flooring and cabinetry.

Explore Our Vinyl Flooring

Should Kitchen Cabinets Be Installed Before or After Flooring?

Kitchen cabinets should generally be installed before floating hybrid and laminate flooring, but some glue-down timber and other fully bonded flooring systems can be installed before cabinetry. The correct order depends on how the flooring attaches to the subfloor, whether it needs room to expand and contract, and whether fixed cabinets or islands will restrict its movement.

A floating floor is not permanently attached to the subfloor. Its connected boards can move slightly as temperature and humidity change. A fully bonded floor, by comparison, is secured to the prepared subfloor using an approved adhesive. This difference determines whether flooring should stop at the cabinet line or continue underneath the cabinets.

Why should kitchen cabinets usually go before floating hybrid and laminate flooring?

Kitchen cabinets and fixed islands should usually be installed before floating hybrid and laminate flooring because their weight and permanent fixings can restrict the floor's natural movement. Floating flooring needs sufficient expansion clearance around fixed objects to accommodate changes in temperature and humidity. Installing heavy cabinetry over it can prevent that movement and contribute to buckling, peaking or joint problems.

Floating hybrid and laminate floors are generally installed as connected boards that move together rather than being fixed directly to the subfloor. When heavy cabinets or islands sit on top, they can hold sections of the floor in place while the surrounding boards continue to expand or contract.

For this reason, the recommended installation approach for many floating systems is:

  1. Install and secure the cabinets first: Fix kitchen cabinets and permanent islands to the appropriate structural support or subfloor, following the cabinet installation requirements.

  2. Prepare the exposed floor area: Check that the remaining subfloor is clean, dry, level and suitable for the flooring system.

  3. Install flooring up to the cabinetry: Cut the floating planks to finish around cabinet bases, island panels and other fixed structures.

  4. Leave the required expansion clearance: Maintain the product-specific gap between the flooring and fixed cabinetry. Do not fill or obstruct this space with materials that prevent movement.

  5. Fit the kickboards and finishing trims: Use the cabinet kickboard or an appropriate finishing profile to conceal the gap without pinning the floating floor.

The required expansion clearance varies between products. Some Australian hybrid and laminate installation guides specify gaps around 8–12 mm, while other products require different allowances. Room dimensions, installation conditions and the manufacturer's instructions determine the correct measurement. Do not apply one expansion-gap figure to every flooring product.

The kickboard should conceal the gap while remaining clear of the floor. Similarly, skirting boards and finishing trims should be secured to the wall or appropriate fixed structure, not through the floating flooring. This allows the floor to move as designed.

Can glue-down timber flooring be installed before kitchen cabinets?

Yes. Some glue-down timber flooring systems can be installed before kitchen cabinets because the adhesive bonds the boards to the prepared subfloor rather than allowing the floor to move freely as a floating surface. Once the adhesive has cured, approved fixed cabinetry and kitchen islands can sit on top of the flooring where the manufacturer's instructions permit it.

This is an important difference between floating and direct-stick installation. A floating engineered timber floor still needs movement clearance around fixed cabinets, even though it is made from timber. A fully bonded engineered timber floor has a different installation structure and may allow heavy fixed items to be installed over it.

Before choosing this sequence, confirm the following:

  • Approved fixing method: Check that the timber product is designed for direct-stick installation and that the proposed adhesive is approved.

  • Subfloor suitability: The subfloor must meet the manufacturer's requirements for moisture, flatness, cleanliness and structural condition.

  • Adhesive curing: Allow the adhesive to cure for the period specified by the flooring and adhesive manufacturers before installing cabinets or placing heavy loads on the floor.

  • Expansion requirements: Check whether the bonded system still requires expansion gaps around walls, fixed structures or other junctions.

  • Installation and warranty conditions: Confirm that installing cabinetry over the finished floor is permitted under the product's installation guide and warranty.

For example, some Australian engineered timber installation guides permit heavy fixed items, including kitchen cabinets and islands, over direct-stick flooring once the adhesive has fully cured. The same products may require floating installations to stop around fixed structures. This demonstrates why the installation method matters as much as the flooring material itself.

Do not assume that every engineered timber or hybrid product can be glued down. Some hybrid boards are designed exclusively for floating installation, while others allow direct-stick installation under specific conditions. Always verify the exact product requirements before scheduling cabinet installation.

Should flooring run underneath kitchen cabinets or stop at the kickboards?

Flooring can either run underneath kitchen cabinets or stop at the cabinet line, depending on the flooring system, installation method and future renovation requirements. Floating floors generally stop before fixed cabinetry, while approved glue-down systems can often extend beneath cabinets. Both approaches have practical advantages and limitations.

Consideration

Flooring underneath cabinets

Flooring stopping at kickboards

Material use

Requires more flooring material

Uses less flooring material

Installation access

Requires flooring installation before cabinetry

Allows cabinets to be installed first

Future cabinet replacement

Provides a finished floor beneath replacement cabinets

May expose an unfinished subfloor if cabinet dimensions change

Floor movement

Suitable for approved bonded systems; can restrict floating floors

Allows floating floors to move independently

Finished appearance

Provides continuous flooring across the room

Creates a neat finish when the cabinet base and kickboard conceal the floor edge

Installation cost

May increase material and installation costs

Can reduce flooring requirements in areas hidden by cabinetry

Installing flooring underneath cabinets

This approach creates a continuous floor surface across the kitchen. It can be useful when installing approved glue-down timber flooring because the cabinets can sit on the bonded surface after the adhesive has cured. It can also make future cabinet replacement easier because flooring already exists beneath the units.

However, installing flooring throughout the kitchen uses more material and may increase installation costs. It is not automatically suitable for floating floors because fixed cabinetry can restrict their movement.

Installing flooring up to the kickboards

This approach is commonly used with floating hybrid and laminate flooring. Cabinet installers secure the fixed units first, and flooring installers fit the boards around the cabinet bases while maintaining the required expansion clearance. The kickboards conceal the exposed edge and expansion space.

This method reduces flooring waste and allows the floating floor to move independently of the fixed cabinetry. However, if the kitchen layout changes later, replacement cabinets with different dimensions may expose areas of unfinished subfloor.

Neither approach is universally better. The right decision depends on the flooring's fixing system, the kitchen layout, the expected lifespan of the cabinetry and the manufacturer's installation requirements.

What happens if kitchen cabinets are installed on top of a floating floor?

Installing fixed kitchen cabinets or islands on top of a floating floor can restrict its movement and increase the risk of installation problems. Depending on the product, room conditions and extent of restraint, the floor may develop buckling, peaking, stressed joints or gaps between boards.

Floating floors are designed to move within the expansion clearances provided during installation. When heavy fixed cabinets hold sections of the floor in place, the boards may not be able to respond freely to temperature and humidity changes.

Potential problems include:

  • Buckling and lifting: Restricted movement can create pressure within the connected floor, potentially causing sections to lift.

  • Peaking: Pressure around board joints can contribute to raised edges or uneven sections.

  • Joint stress: Movement may concentrate around restricted areas, placing additional stress on click-lock connections.

  • Gapping or separation: Uneven movement can contribute to gaps or joint separation in some flooring systems.

  • Warranty complications: Installing cabinetry contrary to the manufacturer's instructions can affect warranty coverage for problems linked to incorrect installation.

These outcomes are not guaranteed with every floating floor. Product construction, installation conditions, floor dimensions and the amount of restraint all influence performance. Some manufacturers have specific approved methods for particular installations, so the product's technical documentation should always take priority.

If fixed cabinets are already installed over a floating floor, do not assume that cutting around the cabinets will automatically solve the problem. A flooring professional should inspect the installation and determine whether the floor has sufficient movement clearance and whether corrective work is required.

The safest approach is to confirm the flooring system before cabinetry installation begins. This allows the cabinetmaker and flooring installer to agree on the floor boundary, expansion clearance and kickboard details before either trade starts work.

Explore Our Carpets

How Does Flooring Type Change the Renovation Order?

Flooring type changes the renovation order because different materials use different installation methods, including floating click-lock, glue-down and loose-lay systems. Floating floors generally need to be installed after fixed kitchen cabinets, while some glue-down floors can be installed before cabinetry. Carpet is usually fitted near the end of the renovation, after painting, cabinetry and other dusty work are complete.

The following table shows how common flooring types affect the installation sequence:

Flooring type

Main installation consideration

Recommended renovation sequence

Hybrid

Often uses a floating click-lock system

Install fixed cabinets first, then fit flooring with the required expansion clearance

Laminate

Commonly uses a floating click-lock system

Install fixed cabinets first and leave the specified movement gap

Engineered timber

Available in floating and glue-down systems

Install cabinets first for floating floors; approved glue-down systems may go underneath cabinets

Vinyl

Available in glue-down, loose-lay and floating click systems

Determine the sequence from the fixing method and manufacturer's instructions

Carpet

Usually installed after major construction and finishing work

Complete painting, cabinetry and dusty work before fitting carpet

Does hybrid flooring go before or after kitchen cabinets?

Hybrid flooring generally goes after kitchen cabinets when the product uses a floating click-lock installation system. Fixed cabinets and kitchen islands should not restrict the floor's movement, so installers usually fit the flooring around the cabinet bases rather than underneath them.

Most floating hybrid floors use interlocking boards that form a connected surface without being permanently attached to the subfloor. Changes in temperature and indoor conditions can cause the floor to expand or contract slightly. Heavy cabinets or fixed islands placed on top can prevent this movement.

A typical installation sequence is:

  1. Complete subfloor preparation and confirm that the surface meets the manufacturer's requirements.

  2. Install and secure fixed kitchen cabinets and islands.

  3. Fit the hybrid flooring around the cabinet bases, island panels and other fixed structures.

  4. Maintain the expansion clearance specified in the product installation guide.

  5. Install kickboards and finishing trims without pinning the floating floor.

The kickboards conceal the floor edge and expansion space while allowing the boards to move freely. Do not fill the required clearance with adhesive, grout or other materials unless the manufacturer's instructions specifically permit it.

Not every hybrid product uses the same installation system. Some products may have different fixing requirements, so check the technical guide before deciding when to install the flooring.

Does timber flooring go before or after kitchen cabinets?

Timber flooring can go before or after kitchen cabinets depending on whether it uses a floating or glue-down installation system. Floating engineered timber generally goes after fixed cabinets, while approved glue-down engineered timber can often be installed beneath cabinetry.

The distinction is important because engineered timber is available in different constructions and installation methods.

Floating engineered timber

Floating engineered timber boards connect through a click-lock or other joining system without being fully bonded to the subfloor. Like floating hybrid and laminate floors, they need room to move.

For this reason, fixed kitchen cabinets and islands are generally installed first. The timber flooring is then fitted around the cabinet bases, with the expansion clearance specified by the manufacturer.

Glue-down engineered timber

Glue-down engineered timber is bonded directly to a suitable subfloor using an approved adhesive. Some systems allow flooring to extend underneath fixed kitchen cabinets because the boards are secured to the substrate rather than moving as a floating surface.

When using this approach, installers must confirm the adhesive, subfloor moisture levels, surface preparation and curing requirements. They should also check whether the product requires expansion clearances around walls or other fixed structures.

Solid timber and engineered timber can also have different installation requirements. Do not assume that every timber floor can be installed beneath cabinetry simply because it is glued down. The manufacturer's approved installation method determines the correct sequence.

Does vinyl flooring go before or after kitchen cabinets?

Vinyl flooring can be installed before or after kitchen cabinets depending on whether it uses a glue-down, loose-lay or floating click system. The installation method, product requirements and cabinet design determine whether the floor can extend underneath fixed cabinetry.

Glue-down vinyl flooring

Glue-down vinyl is bonded to the prepared subfloor using an adhesive approved for the product. Some systems allow the flooring to run underneath kitchen cabinets, provided the manufacturer permits this installation and the adhesive has cured before heavy loads are applied.

Installing glue-down vinyl before cabinetry can create a continuous floor surface. However, the installer must check the substrate, adhesive compatibility, moisture requirements and load restrictions before choosing this sequence.

Floating click vinyl flooring

Click vinyl uses an interlocking system that allows the connected floor to move independently of the subfloor. If the product is designed as a floating floor, fixed cabinets and kitchen islands should generally be installed first.

The installer then fits the vinyl around the cabinet bases and leaves the required expansion clearance. Heavy fixed units should not restrict the floor unless the manufacturer provides a specific approved installation detail.

Loose-lay vinyl flooring

Loose-lay vinyl relies on its weight, backing and installation-specific fixing methods to remain in position. Some products use perimeter adhesive or other approved fixing arrangements, while others have different requirements for larger areas and heavy furniture.

The correct cabinet sequence depends on the manufacturer's instructions. Do not automatically apply the same installation rules to loose-lay, glue-down and click vinyl.

Should carpet be installed before or after painting?

Carpet should generally be installed after painting, kitchen cabinetry and other dusty renovation work because its fibres can collect paint splashes, sanding dust, construction debris and other contaminants. Installing carpet near the end of the project helps protect its appearance and reduces the need for intensive cleaning.

Painting ceilings and walls often involves ladders, tools, sanding and repeated movement around the room. Cabinet installation can also create dust from drilling, cutting and fixing. These activities can leave marks or debris in newly installed carpet.

A practical carpet installation sequence is:

  1. Complete demolition, structural work and service installations.

  2. Finish plaster repairs, sanding, ceiling work and wall painting.

  3. Install kitchen cabinets, benchtops and other fixed fittings.

  4. Complete major floor preparation and ensure the subfloor is clean and suitable.

  5. Install carpet, underlay and appropriate transition profiles.

  6. Complete any remaining skirting-board, door-frame and paint touch-ups carefully.

Carpet is generally installed after the main renovation work, but the exact timing of skirting boards and trims can vary. Some skirting boards are fitted before carpet and others afterwards, depending on the installation detail. The carpet installer should coordinate with the other trades to achieve a neat edge without damaging the finished surfaces.

Overall, hybrid, laminate, timber and vinyl flooring require a sequence based on their fixing systems, while carpet is usually one of the last major finishes installed. Confirming the flooring specification before booking trades helps prevent installation conflicts and unnecessary rework.

Explore Our Laminate Flooring

What Should You Check Before Scheduling Flooring and Cabinet Installation?

Before scheduling flooring and kitchen cabinet installation, check the subfloor condition, finished floor height, cabinet measurements, appliance clearances and installation boundaries. These details help the flooring installer and cabinetmaker coordinate their work, avoid measurement errors and prevent costly adjustments after installation.

Has the subfloor been inspected, levelled and moisture-tested?

Yes. The subfloor should be inspected, repaired, levelled and moisture-tested before installing new flooring. Concrete and timber subfloors must meet the selected flooring manufacturer's requirements for moisture, flatness, cleanliness and structural stability.

A poor subfloor can cause flooring movement, uneven joints, adhesive failure, surface irregularities and premature wear. Installing new flooring without checking the base can also hide moisture problems that become more expensive to repair later.

The inspection requirements depend on the existing subfloor:

Concrete subfloors

Concrete slabs need to be checked for moisture, surface strength, cracks, uneven areas and contaminants. Excess moisture can affect adhesive bonding and cause problems such as timber expansion, flooring movement and adhesive failure.

Before installation, the flooring professional should:

  • Test slab moisture using a method approved for the selected flooring and installation system.

  • Check for cracks, weak concrete, surface coatings and contaminants that could affect adhesion.

  • Assess flatness using the flooring manufacturer's specified tolerance.

  • Grind raised areas and fill depressions with a suitable levelling compound where required.

  • Apply an approved moisture barrier if the flooring system and test results require one.

Timber subfloors

Timber subfloors, including plywood and particleboard, need to be checked for moisture, structural stability, movement and uneven surfaces. Loose boards, damaged sheets and excessive deflection can affect the performance of the new flooring.

The installer should:

  • Check moisture content using an appropriate testing method.

  • Inspect boards and sheets for movement, squeaking, damage and weak sections.

  • Secure loose sections and repair damaged areas.

  • Sand raised joints and prepare uneven surfaces where necessary.

  • Confirm that the subfloor is suitable for the selected underlay, adhesive or floating flooring system.

Cleaning and final preparation

Both concrete and timber subfloors must be clean and free from loose debris, dust, oil, old adhesive residue and other contaminants that could affect installation. Any levelling compounds, repair materials or moisture barriers must also be installed and cured according to their product instructions.

Do not assume that every flooring product has the same moisture or flatness limits. Check the technical installation guide for the exact flooring, adhesive and preparation products before proceeding.

Have you confirmed the finished floor height with the cabinetmaker?

Yes. Confirm the finished floor height with the cabinetmaker before ordering or installing kitchen cabinets because flooring thickness and underlay can affect cabinet dimensions, appliance openings and clearances around doors.

The finished floor height is the final level of the installed flooring surface, including any required underlay or other installation layers. If the cabinetmaker works from the existing subfloor level instead of the planned finished floor level, some components may not fit as intended.

Check the following measurements:

  • Cabinet kickboard height: Confirm that the kickboards can cover the space beneath the cabinets after flooring installation. The cabinet design should allow for the planned floor thickness and installation method.

  • Dishwasher clearance: Check the height and width of the dishwasher opening. A dishwasher may become difficult to remove or replace if the finished floor raises the opening or restricts the appliance's adjustable feet.

  • Oven positioning: Confirm the appliance opening, support requirements and clearance around the oven. The finished floor level should not interfere with the appliance's installation or removal.

  • Refrigerator positioning: Check the available height, width and depth, including any ventilation and door-opening requirements specified by the appliance manufacturer.

  • Door clearance: Account for the additional floor height when checking internal doors, pantry doors and door frames. Some doors may need trimming or adjustment.

  • Room transitions: Measure the height difference between adjoining flooring surfaces so the installer can select suitable transition profiles and avoid unnecessary steps.

For example, installing a thicker hybrid floor with an underlay can raise the finished floor level compared with a thinner vinyl product installed directly over a suitable substrate. The cabinetmaker needs the actual product thickness and installation build-up before finalising the measurements.

Have the flooring installer and cabinetmaker agreed on the installation boundary?

The flooring installer and cabinetmaker should agree on the exact point where the flooring will stop, whether it will extend beneath the cabinets and how the exposed edges and expansion gaps will be finished. This is especially important when installing floating hybrid, laminate or engineered timber flooring.

Without an agreed boundary, the two trades may work from different assumptions. The cabinetmaker might expect flooring to extend beneath the cabinets, while the flooring installer may plan to stop at the cabinet base to preserve movement clearance.

Confirm these details before installation:

  • Flooring boundary: Mark where the flooring will finish around base cabinets, kitchen islands, pantry units and fixed appliances.

  • Expansion clearance: Confirm the required gap around fixed cabinetry and other permanent structures for floating flooring.

  • Kickboard coverage: Check that the kickboards will conceal the flooring edge and expansion space without restricting floor movement.

  • Removable kickboards: Confirm whether the kickboards can be removed if future flooring repairs or appliance access require it.

  • Final measurements: Agree on who will measure the finished floor height, cabinet openings and appliance clearances.

  • Trade responsibilities: Establish who will cut flooring around cabinets, install finishing profiles and complete the final adjustments.

It is also useful to confirm these details in the renovation drawings or written installation scope. This gives the cabinetmaker and flooring installer a shared reference and reduces misunderstandings during the project.

Are the materials and trades booked in the correct order?

Yes. Book materials and trades according to their installation dependencies, product lead times and required curing periods. Flooring, cabinets, benchtops and painting cannot always be scheduled independently because one installation may depend on measurements or preparation completed by another trade.

For example, kitchen cabinets may need to be manufactured before installation, while benchtops often require accurate measurements after the cabinets have been fitted and levelled. Flooring installation may also depend on completed subfloor repairs, moisture testing and the curing of preparation compounds.

Before confirming dates, check the following:

  1. Flooring availability: Confirm that the selected flooring, underlay, trims and installation materials are available before booking the installer.

  2. Cabinet manufacturing: Check cabinet production and delivery lead times, including custom sizes, panels, hardware and kickboards.

  3. Benchtop templating: Allow time for cabinet installation and levelling before the benchtop supplier takes final measurements.

  4. Painting schedule: Complete major painting before vulnerable finished flooring is installed, and allow the required drying time before other trades work against painted surfaces.

  5. Subfloor preparation: Schedule repairs, levelling compounds and moisture treatments early enough to meet their curing and testing requirements.

  6. Flooring installation: Book the flooring installer after confirming the cabinet boundary, finished floor height and subfloor suitability.

  7. Final fit-off: Allow time for kickboards, skirting, trims, appliance connections, paint touch-ups and final adjustments.

Some products require specific acclimatisation, adhesive curing or drying periods. These times vary, so use the instructions supplied by the flooring, adhesive, paint and preparation-product manufacturers rather than assuming a standard waiting period.

Finally, confirm the installation dates, site access, material deliveries and responsibilities of each trade in writing. A coordinated schedule helps prevent one contractor from arriving before the previous work is ready and reduces delays caused by missing materials or incomplete preparation.

Ready to Transform Your Home's Flooring?

Get expert guidance on carpets, hybrid, timber, vinyl & laminate flooring. Book a free in-home consultation with our specialists today!

What Are the Most Common Renovation Sequencing Mistakes?

Common renovation sequencing mistakes include installing floating flooring beneath fixed cabinets, painting after new flooring is fitted, overlooking finished floor height and installing flooring over an unsuitable subfloor. These errors can cause floor movement problems, surface damage, fitting issues, additional labour and unnecessary renovation costs.

Here are seven mistakes to avoid when planning flooring, painting and kitchen cabinet installation.

1. Installing floating flooring beneath fixed kitchen cabinets

Installing floating hybrid, laminate or engineered timber flooring beneath fixed cabinets without manufacturer approval can restrict the floor's natural movement. This may contribute to buckling, raised joints, gaps or other installation problems. Install fixed cabinetry first and maintain the required expansion clearance.

2. Painting after installing new carpet or finished flooring

Painting after flooring installation exposes new surfaces to paint splashes, sanding dust, ladders and equipment marks. Carpet can be particularly difficult to clean when paint enters its fibres, while some hard floors can scratch or stain. Complete the main painting work before installing new flooring and protect finished surfaces during any remaining touch-ups.

3. Ordering cabinetry before confirming the finished floor height

Ordering kitchen cabinets without accounting for flooring thickness and underlay can create problems with kickboard dimensions, appliance openings and door clearances. Confirm the finished floor height and appliance specifications with the cabinetmaker before finalising cabinet measurements.

4. Installing flooring over an unsuitable or damp subfloor

An uneven, contaminated or moisture-affected subfloor can cause uneven flooring, adhesive failure, joint damage and moisture-related problems. Inspect, repair, clean and moisture-test the subfloor before installation. Follow the selected flooring manufacturer's requirements for surface preparation and moisture limits.

5. Fitting kickboards before establishing the final floor height

Installing kickboards before the finished floor level is confirmed can leave visible gaps, incorrect clearances or kickboards that interfere with the flooring. Coordinate kickboard measurements with the flooring installer and fit or adjust them at the appropriate stage.

6. Allowing dusty trades to work over newly installed flooring

Drilling, cutting, sanding and other construction activities can leave debris on finished floors. Heavy equipment and repeated foot traffic can also scratch or dent some surfaces. Complete dusty work before flooring installation wherever possible, and use suitable protective coverings when later work cannot be avoided.

7. Booking the flooring installer before agreeing on cabinet and flooring boundaries

If the cabinetmaker and flooring installer have different assumptions about where the floor should stop, the result can be incorrect expansion gaps, exposed floor edges or unnecessary rework. Agree on the flooring boundary, cabinet positions, kickboard coverage and installation responsibilities before confirming the installation date.

A clear renovation schedule helps prevent these mistakes. Confirm the flooring system, cabinet dimensions, subfloor condition and trade responsibilities before installation begins rather than trying to correct problems after the finishes are in place.

Conclusion

The correct renovation order for flooring, painting and kitchen cabinets depends on the flooring installation method, cabinet design and overall renovation scope. Most wall and ceiling painting should be completed before installing new flooring, while fixed kitchen cabinets generally go before floating hybrid and laminate floors. However, approved glue-down flooring systems may allow the floor to run underneath cabinetry.

Before starting your renovation, confirm the subfloor condition, finished floor height, appliance clearances and installation boundaries with your contractors. Coordinating the cabinetmaker, painter and flooring installer early helps prevent installation problems, protect finished surfaces and reduce unnecessary costs and delays.

Gorkha Flooring supplies and installs quality flooring for Australian homes, helping homeowners choose suitable materials for their spaces and understand the preparation and installation requirements. Whether you're considering hybrid, timber, laminate, vinyl or carpet, our team can help you plan your flooring installation as part of your renovation.

Frequently Asked Questions 

Should I paint or install flooring first?

Complete most wall and ceiling painting before installing new flooring. This reduces the risk of paint splashes, sanding dust, scratches and damage to finished surfaces.

Should kitchen cabinets or flooring be installed first?

Install fixed kitchen cabinets before floating hybrid and laminate flooring. Approved glue-down flooring systems may be installed underneath cabinets, depending on manufacturer requirements.

Can you install hybrid flooring under kitchen cabinets?

Most floating hybrid flooring should not run beneath fixed kitchen cabinets because their weight can restrict floor movement. Follow the product's installation instructions.

Should kitchen cabinets sit on top of laminate flooring?

Generally, no. Floating laminate flooring needs room to expand and contract, so fixed cabinets should sit on the subfloor rather than restrict the flooring.

Do you install skirting boards before or after flooring?

Skirting boards are commonly installed after flooring to cover expansion gaps. However, the correct timing depends on the flooring system and finishing requirements.

Should you install kitchen cabinets before painting?

Complete most wall painting before installing kitchen cabinets because accessible surfaces are easier to prepare and paint. Final touch-ups may be needed after cabinetry installation.

How long should you wait after painting before installing new flooring?

Wait until the paint has dried sufficiently according to the manufacturer's instructions before flooring installation. Drying times vary depending on paint type, temperature and ventilation.

Who should coordinate the flooring and cabinet installation?

The homeowner, builder or renovation project manager should coordinate both trades. The flooring installer and cabinetmaker should confirm measurements, installation boundaries and finished floor heights before work begins.